From: Mark Dennin
Sent: Friday, August 15, 2014 5:27 PM
Subject: Street Closures in the City of Fort Lauderdale
Sent: Friday, August 15, 2014 5:27 PM
Subject: Street Closures in the City of Fort Lauderdale
Traffic Information Updates
Public Affairs is sending this Traffic Update to keep you informed about road closures in the City of Fort Lauderdale. These advisories will continue to be sent on a weekly basis. Please be advised that this report is compiled from multiple sources and agencies that, at times, provide conflicting information. Every effort is made to ensure accuracy; however, due to the fluid nature of road closures, this information is subject to change. This Traffic Update is also posted on the City’s website at http://www.fortlauderdale.gov/Traffic/TrafficUpdate.htm.
Information Regarding Street Closures in the City of Fort Lauderdale
>> NE 55th Street Bridge is Closed for Emergency Repairs; Boat Traffic Not Affected
The NE 55th Street Bridge between Bayview Drive and Federal Highway (U.S. 1) is currently closed for emergency repairs.
During the course of repairs on the bridge, City engineers discovered greater than expected deterioration of some of the support structures. To prevent further damage and as a public safety precaution, the bridge was closed for emergency repairs. Based on preliminary assessments, work is expected to be completed in the next four to six weeks.
In the meantime, motorists may access Federal Highway by way of NE 51st Street, Bayview Drive or Commercial Boulevard.
The waterway under the bridge remains open to boat traffic.
Staff has completed an evaluation of all bridges in the City of Fort Lauderdale as part of a long-term, comprehensive strategy to prioritize needs and allocate the proper resources to maintain and enhance infrastructure while ensuring public safety.
For regular updates, visit www.fortlauderdale.gov or call 954-828-8000.
>> Crews from Florida Department of Transportation’s (FDOT) contractor, Russell Engineering, Inc., and their sub-contractors, began work on this $11.8 million project July 28 and expect to be completed by late December 2015.
The A1A Reconstruction Team thanks our project neighbors for their patience and cooperation during this work.
>> Reconstruction of A1A in Fort Lauderdale – July 28 through December 2014:
East side of A1A between Sunrise Boulevard and NE 14 Court
Parking spaces and sidewalk will be closed on the east side of A1A in this construction zone. Beach access points will be restricted. Pedestrians and beach goers will not be allowed to cut through the work zone. Two-way traffic, bike lane, parking and sidewalk will be maintained on the west side of A1A.
West side of A1A between NE 14 Court and NE 18 Street
Parking spaces and sidewalk will be closed on the west side of A1A in this construction zone. Access will be maintained to side streets and driveways. Two-way traffic, bike lane, parking and sidewalk will be maintained on the east side of A1A.
The contractor is authorized to work Monday through Saturday between 8 a.m. and 7 p.m. The project is expected to be completed in 506 calendar days, however, the contractor can earn a bonus for completing the project up to 100 days early. Note: After this project is completed, landscaping will be installed in the raised median and planter areas along the east side promenade under a separate contract.
If you know someone that would like to receive project email updates, please send their address to Barbara.Kelleher@dot.state.fl.us with a Subject line of A1A Updates and remind them to put this address on their "safe sender" list. Also, you can follow us on Twitter @MyFDOT_SEFL.
>> South Andrews Avenue between SE 27th Street and SE 30th Street (Aug 4 - Sept 12) - The Broward County Highway and Bridge Maintenance Division will be upgrading the drainage system and repairing existing sidewalks and curb ramps along the southbound lanes of South Andrews Avenue, between SE 27th Street and SE 30th Street in Fort Lauderdale. Construction is expected to begin Monday, August 4, 2014 and will conclude on or before September 12, 2014, barring any unforeseen conditions or weather delays. During construction, traffic on the southbound lanes of South Andrews Avenue will be temporarily restricted to one lane, and driveway access to the properties on the west side of South Andrews Avenue may be restricted for very short periods of time. Northbound lanes will not be affected during construction. For more information, contact project Manager Rares Petrica at 954-577-4631 or 954-612-0857 or rpetrica@broward.org.
>> Eller Drive east of the I-595/US 1 interchange at Port Everglades
>> Bridges of the Isles and Sunrise Key Bridges Replacement in Fort Lauderdale
>> I-95 Bridge Painting and Rehabilitation over the South Fork of the New River in Fort Lauderdale
>> Sunrise Boulevard Bridge over the Middle River
>> Signalization Installation Project on State Road 84 at I-95 in Fort Lauderdale
>> Davie Boulevard Roadway Improvements Project in Fort Lauderdale
>> Broward County Transit Improvements in Fort Lauderdale
>> Sunrise Boulevard from NE 26th Ave to Birch Road in Fort Lauderdale
>> US 1 near Port Everglades & Fort Lauderdale/Hollywood International Airport
>> A1A In Action - Enhancing a Piece of Fort Lauderdale's Future (Project construction is expected to last until approximately summer 2016.)
>> Pearl Flagler Village, LLC is building a development along NE 5th Avenue in Fort Lauderdale. They have received approval (Revocable License) from the City Commission to close the following roads (see the MOT Plan ) for a period of 18-months starting on April 1, 2013.
>> I-595 Express Corridor Improvements Project: The Express News - Details at www.i-595.com
Please remember to slow down in construction areas and always buckle up, drive carefully and arrive safely. Share the road.
|